This is what NazmIQ produces from your quotes

Four subcontractor quotes for one LV switchboard package — levelled onto a common scope, converted to one currency, exclusions flagged, totalled with VAT and ranked by weighted score. Generated by the same engine paying customers use; the data is an illustrative sample.

What the levelling did

Three things these four quotes disagreed on — resolved before the totals

Every point below is visible in the report underneath. This is the work that makes the comparison apples-for-apples.

1

One bidder priced in a different currency

Gamma Switchgear quoted in USD, the other three in EUR. On the raw numbers Gamma’s MDB looks identical to Beta’s — both read 52,000 — but converted at 1 EUR = 1.08 USD it is about 7% cheaper. Every rate was converted line by line, and the rate used is printed on the report.

See Exchange Rates Used · the FX-risk row flags the exposure that comes with it
2

One bidder left an item out — so its total was never comparable

Beta Power Systems never priced the Automatic Transfer Switch. Leave that blank and Beta looks cheaper than it is: a quote can win simply by covering less. The bidders who did price it ranged from €7,870 to €24,000 — real money you would buy later as a variation.

So the gap is levelled, not just flagged. The rate from the most complete quote (Delta Controls, €8,000) is carried into the blank cell and the cell is shaded amber — exactly what an estimator does by hand, and the report names the vendor it borrowed from. Beta’s as-quoted total stays visible at €108,491; the levelled total it is actually ranked on is €117,691. Its scope completeness drops to 90 (9 of 10 items) while the rest hold 100, and it lands 3rd.

See the amber ATS cell in the detailed breakdown · the levelling note beneath the totals · Items Not Quoted in the risk matrix
3

Everyone named the same items differently

Four quotes, four naming conventions — abbreviations, reversed word order, spec suffixes. Each was matched onto one master scope row so the rates sit side by side instead of in four unrelated lists:

Levelled to Alpha ElectricBeta Power SystemsGamma SwitchgearDelta Controls
Main Distribution Board (MDB) Main Distribution Board — MDB MDB (main board), Form 4 Type 2 Main LV Panel / MDB Main Switchboard (MDB)
Sub-MDB Floor 1 SMDB-01 (Level 1) Sub Main Distribution Board Fl.1 SUB-MDB L1 Sub-board, first floor
Automatic Transfer Switch (ATS) ATS 1600A — not priced — Auto Transfer Switch (A.T.S) Changeover switch — automatic
The report below shows only the levelled names — that is the point

Meridian Contracting Ltd. – Metro Hospital — Electrical Package

LV Switchboards Comparison

✅ Recommendation
Gamma Switchgear is recommended — the highest overall score (91/100) under the current evaluation weighting, at the lowest total on equal scope, 5–6 months delivery. Caveats to confirm before award: fx / currency risk (USD-based; exchange-rate moves change the EUR price). Note: this vendor quoted in USD, converted to EUR at the rate shown.
💰 Financial Summary
Line ItemAlpha ElectricBeta Power SystemsGamma SwitchgearDelta Controls
Total (ex-VAT)€117,960.00€94,340.00€82,962.95€89,570.00
VAT€17,694.00 (15%)€14,151.00 (15%)€12,444.44 (15%)€13,435.50 (15%)
Total as quoted — covers different scope€135,654.00€108,491.00€95,407.39€103,005.50
TOTAL — levelled to equal scope (incl. VAT) †€135,654.00€117,691.00 (†1)€95,407.39€103,005.50
Savings vs. Highest Bidder (levelled)€0.00€17,963.00€40,246.61€32,648.50
Advance Payment€67,827.00 (50%)€54,245.50 (50%)€38,162.96 (40%)€30,901.65 (30%)
Compare on the levelled total, not the as-quoted one. The as-quoted totals cover different amounts of work, so a supplier with gaps looks cheaper simply for having offered less. Items a supplier did not price are carried at rates from Delta Controls, which puts every total over the same scope; those cells are shaded in the detailed table. Ranking, scoring and savings all use the levelled total — the as-quoted row is shown so you can see how large each gap is.
Gaps filled — Beta Power Systems (1 of 10).
🏆 Weighted Evaluation
Evaluation CriterionWeightAlpha ElectricBeta Power SystemsGamma SwitchgearDelta Controls
Price Competitiveness60%70.381.1100.092.6
Delivery Period15%65.080.060.075.0
Payment Terms10%80.070.075.065.0
Scope Completeness10%100.0
10/10 items
90.0
9/10 items
100.0
10/10 items
100.0
10/10 items
Brand / Certification5%95.092.088.090.0
TOTAL WEIGHTED SCORE (max 100)74.781.390.987.8
RANK4th🥉 3rd🥇 1st🥈 2nd
📦 Delivery Timeline
Alpha Electric
4–6 mo
Beta Power Systems
3–4 mo
Gamma Switchgear
5–6 mo
Delta Controls
4–5 mo
Bar length = delivery lead time (months). Shortest = fastest.
⚠️ Risk / Gap Analysis
Risk / GapSeverityAlpha ElectricBeta Power SystemsGamma SwitchgearDelta Controls
Items Not QuotedLow1 of 10 items not priced
Offer ValidityMedium1 month ✓2 weeks — confirm30 days ✓1 month ✓
FX / Currency RiskMediumNone — EURNone — EUR⚠ USD-based; exchange-rate moves change the EUR priceNone — EUR
Delivery RiskMedium4–6 mo — acceptable3–4 mo — fastest ✓5–6 mo4–5 mo
💱 Exchange Rates Used
1 EUR = 1.0800 USD
Rates as of illustrative sample
📋 Detailed Comparison
#Item DescriptionUnitQtyAlpha ElectricBeta Power SystemsGamma SwitchgearDelta Controls
Unit Rate (EUR)Total (EUR)Unit Rate (EUR)Total (EUR)Unit Rate (EUR)Total (EUR)Unit Rate (EUR)Total (EUR)
SupplierAlpha ElectricBeta Power SystemsGamma SwitchgearDelta Controls
Reference No.AE-Q-2026-018BPS-1142GS-INT-0459DC-2026-231
Date10/06/202612/06/202608/06/202611/06/2026
Validity1 month2 weeks30 days1 month
Payment Terms50% advance / 50% on delivery50% advance / 50% on delivery40% advance, balance on delivery30% advance / 70% on delivery
Delivery Terms4–6 months3–4 months5–6 months4–5 months
CurrencyEUREURUSD → EUR @ 1.08EUR
★ 1 EUR = 1.0800 USD (illustrative sample rate). Gamma Switchgear quoted in USD; all figures converted to EUR.
MAIN BOARDS
1Main Distribution Board (MDB)set158,000.0058,000.0052,000.0052,000.0048,148.1548,148.1555,000.0055,000.00
2Emergency MDB (EMDB)set114,500.0014,500.009,800.009,800.008,333.338,333.336,000.006,000.00
3Automatic Transfer Switch (ATS)set124,000.0024,000.008,000.00 †8,000.007,870.377,870.378,000.008,000.00
Subtotal — MAIN BOARDS96,500.0069,800.0064,351.8569,000.00
SUB-DISTRIBUTION BOARDS
4Sub-MDB Floor 1pcs15,200.005,200.0012,000.0012,000.004,444.444,444.444,500.004,500.00
5Sub-MDB Floor 2pcs19,500.009,500.0012,500.0012,500.008,148.158,148.159,000.009,000.00
6Sub-EMDB Floor 1pcs12,800.002,800.004,000.004,000.002,314.812,314.812,500.002,500.00
Subtotal — SUB-DISTRIBUTION BOARDS17,500.0028,500.0014,907.4016,000.00
DISTRIBUTION & AC PANELS
7Distribution Panel DP-1pcs1720.00720.00780.00780.00722.22722.22880.00880.00
8Distribution Panel DP-2pcs1740.00740.00820.00820.00759.26759.26920.00920.00
9AC Panel AC-1pcs11,200.001,200.001,180.001,180.001,064.811,064.811,330.001,330.00
10AC Panel AC-2pcs11,300.001,300.001,260.001,260.001,157.411,157.411,440.001,440.00
Subtotal — DISTRIBUTION & AC PANELS3,960.004,040.003,703.704,570.00
Total (ex-VAT)117,960.0094,340.0082,962.9589,570.00
VAT17,694.0014,151.0012,444.4413,435.50
GRAND TOTAL (incl. VAT)135,654.00108,491.0095,407.39103,005.50
Savings vs. Highest Bidder0.0017,963.0040,246.6132,648.50
Advance Payment67,827.0054,245.5038,162.9630,901.65
% vs. Lowest Bidder42.2%23.4%0.0%8.0%